Current:Home > ContactMassachusetts budget approval allows utilities to recoup added cost of hydropower corridor -USAMarket
Massachusetts budget approval allows utilities to recoup added cost of hydropower corridor
View
Date:2025-04-14 22:32:00
PORTLAND, Maine (AP) — A budget signed by Massachusetts Gov. Maura Healey this week will allow utilities to raise rates to make up for hundreds of millions of dollars in additional costs to complete a transmission line to bring Canadian hydropower to the New England electricity grid.
The head of Central Maine Power Co.'s corporate parent Avangrid has said the cost of the $1 billion project grew to $1.5 billion as litigation delayed construction and inflation caused prices to creep upward.
Legislation included the supplemental budget adopted Monday allows transmission service agreements to be renegotiated and additional costs to be passed along to Massachusetts ratepayers to cover the added costs.
Avangrid provided the increased costs to Massachusetts’ electricity distribution companies to adjust the rate in the parties’ transmission services agreements, which would be subject to Department of Public Utilities review and approval, Avangrid spokesperson Leo Rosales said in a statement Tuesday.
He praised Healey and lawmakers for taking action to “deliver this critical project and needed clean power to benefit the entire New England region.”
Avangrid partnered with Hydro-Quebec on the New England Clean Energy Connect to supply 1,200 megawatts of hydropower to meet green energy goals in Massachusetts. That would be enough electricity to power about a million homes.
The 145-mile (233-kilometer) transmission line will stretch from Lewiston, Maine, to the Canadian border.
It received all regulatory approvals but was plagued by delays, litigation and a referendum in which https://apnews.com/article/election-2021-maine-hydropower-line-54dea1a948e9fc57a667280707cddeb7
It was allowed to move forward after a Maine jury concluded that the developers had a constitutional right to proceed despite the referendum.
Construction resumed in August on a transmission hub that’s critical to the project in Lewiston. But it’s unclear when other work will restart.
Workers had already begun removing trees and setting utility poles on a disputed portion of the project, a new 53-mile (85-kilometer) section cut through the woods in western Maine, before the project was put on hold.
The project was envisioned to meet Massachusetts’ clean energy goals, and the cost is fully borne by ratepayers in that state.
However, supporters say electricity would lower energy costs across New England as well as reduce carbon pollution.
veryGood! (68397)
Related
- Juan Soto to be introduced by Mets at Citi Field after striking record $765 million, 15
- What role will Zach Ertz play for the Lions? Highlights, stats of TE's 11-year career
- Could Champagne soon stop producing champagne?
- Taylor Swift attends Kansas City Chiefs playoff game against the Buffalo Bills at Highmark Stadium
- Taylor Swift Eras Archive site launches on singer's 35th birthday. What is it?
- California woman arrested in theft of 65 Stanley cups — valued at nearly $2,500
- 2024 NFL draft order: Top 28 first-round selections set after divisional playoffs
- Baseball Hall of Fame discourse is good fun – but eye test should always come first
- Hackers hit Rhode Island benefits system in major cyberattack. Personal data could be released soon
- A woman dies and 2 people are injured at a French farmers’ protest barricade
Ranking
- Civic engagement nonprofits say democracy needs support in between big elections. Do funders agree?
- Maine Democrats who expanded abortion access now want to enshrine it in the state constitution
- In Washington state, pharmacists are poised to start prescribing abortion drugs
- How many delegates does New Hampshire have for the 2024 primary, and how are they awarded?
- Grammy nominee Teddy Swims on love, growth and embracing change
- Families sue Kentucky gun shop that sold AR-15 used in 2023 bank shooting that killed 5
- TikTok cuts jobs as tech layoffs continue to mount
- Baseball Hall of Fame discourse is good fun – but eye test should always come first
Recommendation
Finally, good retirement news! Southwest pilots' plan is a bright spot, experts say
Floridians wait to see which version of Ron DeSantis returns from the presidential campaign trail
Baseball Hall of Fame discourse is good fun – but eye test should always come first
Canada is capping foreign student visas to ease housing pressures as coast of living soars
Nearly 400 USAID contract employees laid off in wake of Trump's 'stop work' order
Against a backdrop of rebel attacks and border closures, Rwanda and Burundi trade accusations
Western Balkans countries pledge support for new EU growth plan, as they seek membership in the bloc
Ticket prices for AFC, NFC championship game: Cost to see Chiefs vs. Ravens, Lions vs. 49ers